Over the last year or so FSD have completed the Electrical and Instrumentation Installation works associated with Membrane plants for Thames Water, Three Valleys Water, Portsmouth Water and Severn Trent Water.
Our most recent Membrane project is with Gleesons, at Scottish Water’s Invercannie site, which is located approximately 30 miles West of Aberdeen.
The works at Invercannie are mainly within the new Membrane building, where we have had to work closely with all other disciplines to ensure that the tight programme of works is met and that there are no installation clashes. With over 30,000m of cable to install amongst the plant and pipework this was no mean feat and the praise that we have received from both our client and Scottish Water reflects heavily on the quality of our site installation team and the relationships they have built on site.